Repair could keep vital water capacity running as regulators step up scrutiny
Deciding that an ageing concrete tank can be repaired rather than replaced is only part of the challenge for water companies. The harder question is often how to carry out the work while a treatment works still needs its capacity and keeps meeting its environmental obligations.
Those obligations are under close scrutiny. The first joint report from the sector’s four regulators, published last month, recorded 2,991 pollution incidents across England and Wales in 2025, 84 of them serious. In England, the Environment Agency’s annual assessment gave the sector 16 stars out of a possible 36.
But according to Roger Line, founder and CEO of Structural Repairs, planning an outage deserves as much attention as designing the repair itself, and the first question should be whether the investigation and repair can be designed around the way the site operates.
He said: “As demand grows and spare capacity becomes more constrained, taking an asset out of service can be a major operational challenge.
“Depending on the asset and the defect, work may be possible from outside the structure, in phases or within a locally isolated area while the wider treatment process continues. Other situations need a planned outage. The right approach depends on safety, access, water quality and the structure itself.”
He pointed to a recent project at a water treatment site, where Structural Repairs rehabilitated concrete within a distribution chamber while the process remained operational outside the isolated work zone, with containment protecting the live process water.
Repairs can include targeted injection, concrete repairs and composite strengthening, but scanning comes first, showing where work is genuinely needed rather than assuming the whole structure requires the same treatment.
“A short scan doesn’t necessarily mean a short outage,” Mr Line said. “Preparation, access, reinstatement and returning the asset to service can take longer than the testing itself.”
Owners, he added, should separate how long a project lasts from how long an asset is actually out of action. “A phased repair carried out while the asset stays in service can have a very different operational impact from an offline repair, even if the calendar period is similar.”
Sometimes the investigation can avoid a drain-down altogether. Where an external face of a tank or channel is accessible, it can be assessed from outside, although the wall’s make-up, moisture and the type of defect limit what can be established.
“If a crack continues below ground, scanning the exposed section doesn’t tell you how far it goes,” Mr Line said. “That may need internal access, controlled excavation or another suitable method.”
When repair goes ahead with the asset in service, the work may be broken into sections and timed around lower-flow periods. Changing flows, weather, the treatment capacity still available and the risk of unplanned overflows all have to be built into the plan.
He said: “You have to plan the work around the operating constraints rather than assume the whole structure is available at once.”
Not every job can be done live. Confined spaces, harmful gases, flooding and rescue arrangements each need a site-specific safe system of work, and where those risks cannot be controlled with the asset operating, a planned shutdown becomes part of the solution. Drinking-water work also needs its own product-specific and project-specific assessment.
Hydrogen sulphide damage shows why the operating environment has to shape the repair. In sewage environments, bacteria can convert hydrogen sulphide into sulphuric acid, which attacks concrete, and that exposure carries on once the asset returns to use.
He said: “You need to establish the extent and cause of the damage, the remaining section and the operating conditions first. The repair design has to consider the continuing exposure as well as the damage that’s already there.”
For asset owners weighing up their options, Mr Line said the meaningful comparison covers the whole intervention: access, temporary works, any temporary treatment capacity and the return to service, as well as the repair.
He said: “The programme depends on the assessed scope. Owners need a credible programme for the whole job, not just the time spent scanning or applying a repair. The aim is simple: understand the asset, target the work, verify the result and preserve as much operating capacity as safely possible.”